A take-off is the list of quantities a contractor prices from. Two bids for the same room can differ just because each bidder measured it differently. If you hand out your own numbers, every bid starts from the same place. This calculator runs in your browser. It does not send what you type anywhere, and it does not save it.
Door openings, open sides, and any edge where two of your rectangles join. Count a shared edge twice, once for each rectangle.
Enter a length and a width to see the totals.
How to measure
- Measure wall to wall at floor level, in feet. Round to the nearest half foot. The installer will measure again at the site visit.
- Enter inches as a decimal. 3 inches is 0.25 ft, 6 inches is 0.5 ft and 9 inches is 0.75 ft.
- Measure the whole room, including the floor under equipment that will be moved out for the job. Leave out floor under equipment that stays bolted down, and say so on the sheet.
- Walk the edge of the room and add up every stretch that needs no cove base: doorways, dock doors, open sides. That total goes in the "no cove base" box.
- Count every floor drain, including trench drains. Note a trench drain's length next to the count.
What each number is for
| Number | Why a bidder needs it |
|---|---|
| Square feet | The main quantity. Some costs don't shrink with the room, so a small area costs more per square foot. The cost guide explains why. |
| Cove base, linear feet | A cove base carries the floor a few inches up the wall so the two meet without a seam. It is hand work, and it should be its own line on the bid, priced by the linear foot. |
| Drains | Each drain takes extra prep. On one maker's data sheet, the concrete around each drain is chipped down and tapered back. The floor prep guide has the detail. |
| Columns and pads | More edges to detail by hand, and more cove base if you want it around them. Ask each bidder how they are handled. |
What this does not do
It is not a quote. It does not estimate material, labor or price. Those depend on the system, its thickness and the state of your slab, and nobody can judge the slab from a web page. The numbers here are for getting like-for-like bids. The contractor's own measurements are the ones a contract is written on.
Keep reading
- What drives cost: why two bids for the same room can be far apart.
- Bid comparison worksheet: line up to three bids against the same checklist and print it.
- Downtime cost calculator: what each bid costs once the closed hours are counted.
You reach the owner, the same person who looks at the floor, prices the job and runs the install. How this works.