Two bids can be thousands of dollars apart and still cost you the same, or the other way round, once you count the hours you can't use the room. Different resins cure at very different speeds, and that is usually where the hours come from. This calculator adds the two together. It uses only the numbers you type. It does not send them anywhere, and it does not save them.
Your own figure. The section below shows one way to work it out. Type plain numbers, with no commas or dollar signs.
Enter your hourly figure and at least one bid.
Where the hours come from
Ask every bidder for an hour-by-hour schedule in writing. It should show when the room must be empty, when prep starts, when each coat goes down, and when you can walk on it, roll carts on it and drive forklifts on it. In a food space it should also show when food and packaging can come back.
Cure time is the big difference between resin types. The acrylic vs. epoxy guide covers why, with the manufacturers' published figures. Odor control can add hours of its own. Setting up containment and fans takes time, and the room may need to air out before it is used again. The odor guide explains what to plan for.
Working out what an hour costs you
There is no standard figure. It comes from your own books. Add up what a closed day costs, then divide by the hours you would normally run that day.
- Lost production or sales that you can't make up later. Count the margin you lose, not the full sale price.
- Wages paid to people who can't do their work while the room is closed.
- Moving and storing product. Refrigerated trailers, rented cold storage, hauling stock out and back.
- Catching up. Overtime or an extra shift to rebuild inventory afterward.
Hours you would be closed anyway cost you nothing extra. A plant that never runs on Sunday, or a kitchen that is dark overnight, has free hours. That is why the calculator asks for them. Night and weekend work can cost more on the bid itself, so check whether each price already includes it.
What this does not tell you
It compares cost, not floors. It can't tell whether two bids describe the same system at the same thickness, or whether the prep is the same. A cheaper total is not a better floor. Check what each bid includes with the bid comparison worksheet before you compare the totals.
Keep reading
- Acrylic vs. MMA vs. epoxy: which resin fits a cold or busy building.
- What drives cost: why two bids for the same room can be far apart.
- Bid comparison worksheet: line up to three bids against the same checklist and print it.
You reach the owner, the same person who looks at the floor, prices the job and runs the install. How this works.